Unexpected Maintenance - Critical Backup Data Center Power Upgrades
Scheduled for Feb 14, 01:00 - 06:00 AEDT
Scheduled
Please be advised that our backup data centre provider will be performing emergency remediation works to mitigate the power issues experienced early this morning.

The provider intends to synchronise multiple UPS units and bring them online tomorrow morning between 1am and 6am AEDT. (February 14th 2018).

No further impact is expected, but due to the elevated risk of the works, the remediation work has been moved outside of business hours.

If you have any questions regarding this unexpected maintenance, please contact the network operations team at noc@hostednetwork.com.au or on 1300 781 148
Posted 10 months ago. Feb 13, 2018 - 17:09 AEDT